# SharePoint On-Premises to Cloud: Migration Strategy Guide for IT Leaders | AvantIT

> A practical decision framework for CTOs and IT Directors planning SharePoint migration to Microsoft 365. Real timelines, costs, and risk mitigation strategies.
Canonical: https://www.avantit.pt/en/blog/sharepoint-migration-cloud-strategy-guide/
Source: AvantIT — https://www.avantit.pt (Microsoft Solutions Partner, Matosinhos, Portugal)

---

[Back to blog](https://www.avantit.pt/en/blog/) 
![SharePoint On-Premises to Cloud: Migration Strategy Guide for IT Leaders]
 SharePoint 

# SharePoint On-Premises to Cloud: Migration Strategy Guide for IT Leaders

 
![Arsénio Ferraz]
 Arsénio Ferraz 2026-02-23 10 min 

SharePoint on-premises reached end-of-support timelines, but migration to Microsoft 365 isn't just a technical lift-and-shift—it's a strategic transformation that requires careful planning, risk management, and executive buy-in.

## Why Migration Urgency is Real

### Support and Security Timeline Pressure

Microsoft’s support lifecycle for SharePoint Server versions:

 

- SharePoint 2013 : Mainstream support ended April 2018, Extended support ends April 2023

- SharePoint 2016 : Mainstream support ends July 2021, Extended support ends July 2026

- SharePoint 2019 : Mainstream support ends July 2024, Extended support ends July 2029
 

Running unsupported versions exposes organizations to:

 

- Security vulnerabilities with no patches

- Compliance and audit risks

- Inability to integrate with modern Microsoft 365 features

- Difficulty recruiting talent skilled in legacy platforms
 

### The Business Case Beyond Compliance

At [Avantit](https://www.avantit.pt/en/), we help clients build comprehensive business cases that go beyond “we must migrate”:

Cost Savings :

 

- Eliminate datacenter costs ($50K-200K annually for mid-sized farms)

- Reduce IT staff time on infrastructure maintenance (1-2 FTEs typically)

- Remove upgrade and patch management overhead
 

Business Enablement :

 

- Modern collaboration with Teams integration

- Mobile access and external sharing

- AI-powered search and content discovery

- Integration with Power Platform for automation
 

Risk Reduction :

 

- Built-in disaster recovery and business continuity

- Enterprise-grade security and compliance tools

- Automatic updates without downtime
 

## Migration Approaches: Three Paths with Different Trade-offs

### Approach 1: Lift-and-Shift (Fastest, Highest Technical Debt)

Timeline : 2-4 months for typical 2TB environment Best for : Organizations under urgent timeline pressure (support ending soon)

Process :

 

- Inventory all sites, libraries, workflows, customizations

- Use migration tools (ShareGate, SharePoint Migration Tool, AvePoint)

- Move content “as-is” to SharePoint Online

- Address broken customizations post-migration
 

Pros :

 

- Fastest path to cloud

- Lowest initial cost

- Minimal business disruption
 

Cons :

 

- Carries forward all legacy baggage

- InfoPath forms and legacy workflows break

- Custom solutions require rework

- Misses opportunity for modernization
 

Real Cost : $30K-80K for consulting + tools (100-500 users)

### Approach 2: Redesign and Migrate (Balanced)

Timeline : 4-8 months for typical environment Best for : Most organizations seeking balance between speed and modernization

Process :

 

- Audit current state and identify modernization opportunities

- Redesign site architecture for modern SharePoint patterns

- Convert InfoPath forms to Power Apps

- Rebuild workflows in Power Automate

- Migrate content to new structure

- Train users on new paradigm
 

Pros :

 

- Modernizes while migrating

- Removes legacy technical debt

- Improves user experience

- Sets foundation for future capabilities
 

Cons :

 

- Longer timeline

- More change management needed

- Higher initial cost

- Requires careful planning
 

Real Cost : $80K-200K for consulting + tools (100-500 users)

### Approach 3: Transform to Microsoft 365 Ecosystem (Strategic)

Timeline : 6-12 months Best for : Organizations ready for comprehensive digital workplace transformation

Process :

 

- Rethink collaboration strategy (not just SharePoint)

- Design integrated Microsoft 365 experience (Teams, SharePoint, Power Platform)

- Migrate content to appropriate modern platforms

- Implement governance and information architecture

- Build Center of Excellence for ongoing optimization
 

Pros :

 

- Maximizes Microsoft 365 investment

- Creates modern digital workplace

- Enables new ways of working

- Strong governance foundation
 

Cons :

 

- Longest timeline

- Significant change management

- Highest consulting investment

- Requires executive sponsorship
 

Real Cost : $150K-500K for comprehensive program (100-500 users)

## The Decision Framework: Choosing Your Path

### Assessment Questions for IT Leaders

1. How urgent is your timeline?

 

- Support ending in < 12 months → Consider Lift-and-Shift or Balanced

- Support ending in 12-24 months → Balanced or Transform

- Support ending in 24+ months → Transform
 

2. What’s your customization complexity?

 

- Minimal (mostly out-of-box) → Lift-and-Shift viable

- Moderate (some InfoPath, workflows) → Balanced recommended

- Heavy (custom solutions, integrations) → Transform or Balanced
 

3. What’s your change capacity?

 

- Low (IT stretched thin) → Lift-and-Shift, address debt later

- Moderate (can dedicate resources) → Balanced

- High (dedicated transformation team) → Transform
 

4. What’s your strategic vision?

 

- Maintain status quo → Lift-and-Shift

- Modernize collaboration → Balanced

- Reinvent digital workplace → Transform
 

## Real Migration Timelines and Resource Requirements

Based on Avantit’s experience with 50+ migrations:

### Small Organization (100-250 users, 500GB-2TB)

Lift-and-Shift :

 

- Timeline: 8-12 weeks

- Internal FTE: 0.5 (IT lead)

- External consulting: 200-300 hours

- Migration tools: ShareGate or SPMT
 

Balanced :

 

- Timeline: 16-24 weeks

- Internal FTE: 1.0 (IT lead + power users)

- External consulting: 400-600 hours

- Migration tools: ShareGate + Power Platform licenses
 

### Mid-Size Organization (250-1000 users, 2-10TB)

Lift-and-Shift :

 

- Timeline: 12-20 weeks

- Internal FTE: 1-2 (IT team + project manager)

- External consulting: 400-800 hours

- Migration tools: Enterprise migration platform
 

Balanced :

 

- Timeline: 24-40 weeks

- Internal FTE: 2-3 (IT team + business analysts + change lead)

- External consulting: 800-1500 hours

- Migration tools: Enterprise platform + Power Platform
 

### Enterprise (1000+ users, 10TB+)

Balanced or Transform :

 

- Timeline: 40-52 weeks

- Internal FTE: 4-6 (dedicated transformation team)

- External consulting: 1500-3000+ hours

- Migration tools: Enterprise platform + full Microsoft 365 stack
 

## Common Migration Risks and Mitigation Strategies

### Risk 1: Broken Customizations

Impact : Custom web parts, event receivers, InfoPath forms fail in cloud

Mitigation :

 

- Inventory all customizations during planning phase

- Classify as: migrate as-is, rebuild modern, retire/replace

- Build SPFx alternatives for critical custom web parts

- Convert InfoPath to Power Apps (plan 40-80 hours per complex form)
 

### Risk 2: Workflow Disruption

Impact : SharePoint 2010/2013 workflows don’t work in SharePoint Online

Mitigation :

 

- Document all active workflows during inventory

- Prioritize by business criticality

- Rebuild critical workflows in Power Automate (20-60 hours per workflow)

- Accept temporary manual workarounds for low-priority flows
 

### Risk 3: Performance Issues Post-Migration

Impact : Users complain about slow sites, search problems

Mitigation :

 

- Implement proper site architecture (hub sites, not nested subsites)

- Configure search crawl schedules appropriately

- Optimize large lists/libraries (use metadata, column indexing)

- Set realistic expectations about initial search index build (days to weeks)
 

### Risk 4: User Adoption Failure

Impact : Users continue working around new system, ROI not realized

Mitigation :

 

- Start change management early (not just training at go-live)

- Identify and train champions in each business unit

- Create role-specific training (not generic)

- Provide ongoing support channel (not just day-one help)
 

### Risk 5: Data Loss or Corruption

Impact : Critical content missing or damaged post-migration

Mitigation :

 

- Multiple test migrations before production cut-over

- Maintain read-only on-premises environment for 90 days post-migration

- Implement versioning in SharePoint Online before migration

- Have rollback plan for critical workloads
 

## The Avantit Migration Methodology

At [Avantit](https://www.avantit.pt/en/), we follow a proven 6-phase approach:

### Phase 1: Discovery & Assessment (2-3 weeks)

 

- Site inventory and usage analysis

- Customization and integration audit

- User interviews and pain point analysis

- Risk and dependency mapping

- Approach recommendation and cost model
 

### Phase 2: Planning & Design (3-4 weeks)

 

- Target architecture design

- Migration wave planning (which content when)

- Customization redesign specifications

- Test plan and success criteria definition

- Change management and training strategy
 

### Phase 3: Pilot (4-6 weeks)

 

- Migrate 2-3 representative sites

- Test all migration patterns

- Validate customization rebuilds

- Conduct user acceptance testing

- Refine approach based on learnings
 

### Phase 4: Wave Migration (8-20 weeks depending on size)

 

- Execute migration in planned waves

- Monitor and troubleshoot issues

- Provide daily user support

- Track success metrics

- Adjust approach as needed
 

### Phase 5: Hypercare (4-8 weeks post-migration)

 

- Intensive user support

- Performance tuning and optimization

- Address outstanding issues

- Knowledge transfer to IT team
 

### Phase 6: Optimization & Governance (Ongoing)

 

- Establish Center of Excellence

- Implement ongoing governance

- Plan next evolution (Teams, Power Platform)

- Measure and report on realized benefits
 

## Cost Considerations: Beyond the Migration Project

### Ongoing Microsoft 365 Costs

Licensing :

 

- Microsoft 365 E3: $36/user/year

- Microsoft 365 E5: $57/user/year

- SharePoint Plan 1: $5/user/month (if not buying full M365)
 

Change from On-Premises :

 

- Eliminate: Hardware refresh, datacenter, SQL licensing, backup infrastructure

- Add: Per-user cloud licensing, potential egress costs for heavy API usage
 

Net Financial Impact : Most organizations see 20-40% cost reduction vs. on-premises total cost of ownership over 5 years.

### Unexpected Costs to Budget For

 

- Storage overages : Plan for growth, default quotas often insufficient

- Power Platform licensing : If rebuilding workflows/forms at scale

- Advanced security features : Some scenarios require E5 or add-on licenses

- Migration tool licensing : Often charged per user or GB migrated

- Extended consulting : Complex issues often require more hours than planned
 

## The Bottom Line for IT Leaders

SharePoint migration is inevitable for most organizations, but the “when” and “how” are strategic decisions with multi-year implications.

Good migrations are characterized by:

 

- Executive understanding and support

- Realistic timelines (don’t rush what can be done properly)

- Balanced investment in technology and change management

- Clear success criteria beyond “content moved”
 

Failed migrations typically share:

 

- Treating it as purely technical project

- Underestimating customization complexity

- Skipping pilot phase

- Inadequate user training and support
 
 

Ready to plan your SharePoint migration?

[Contact Avantit](https://www.avantit.pt/en/contact/) for a complimentary Migration Readiness Assessment. In a 2-hour workshop, we’ll:

 

- Review your current SharePoint environment

- Identify migration complexity and risks

- Recommend the right approach for your situation

- Provide high-level timeline and budget estimates

- Answer your specific concerns and questions
 

Our assessments are honest and consulting-focused—we’ll tell you if you’re not ready to migrate yet and what to do first.

 

#### Editorial Policy

 

At Avantit, we value authenticity and human expertise. This article was written and reviewed by our experts, ensuring technical accuracy grounded in real-world projects. We do not publish content generated exclusively by AI without validation by one of our consultants.

 

### Share and Comment

 Share: [Comment on LinkedIn](https://www.linkedin.com/company/avantit/posts/) 

### Enjoyed this article?

 

Subscribe to our newsletter to receive more content like this or contact us to learn how we can implement these solutions in your company.

 

### Looking for something?

 

### Most Read

 01 [An Intranet in Days, Not Months: How SharePoint Templates Accelerate Implementation](https://www.avantit.pt/en/blog/sharepoint-templates-fast-intranet/) 02 [The Hidden Cost of Manual Data Entry: What CFOs Need to Know](https://www.avantit.pt/en/blog/hidden-cost-manual-data-entry-cfos/) 

### Weekly Tip

 

Use o Power Toys no Windows para extrair texto de qualquer imagem com o atalho Win+Shift+T . Aumenta a produtividade em 30%!

 

### Categories

 
- [SharePoint 5](https://www.avantit.pt/en/blog/?category=SharePoint)
- [Power Platform 5](https://www.avantit.pt/en/blog/?category=Power%20Platform)
- [Business Strategy 4](https://www.avantit.pt/en/blog/?category=Business%20Strategy)
- [Modern Work, Governance 2](https://www.avantit.pt/en/blog/?category=Modern%20Work%2C%20Governance)
- [Compliance & Security 1](https://www.avantit.pt/en/blog/?category=Compliance%20%26%20Security)
- [SharePoint & Modern Work 1](https://www.avantit.pt/en/blog/?category=SharePoint%20%26%20Modern%20Work)
- [AI & Automation 1](https://www.avantit.pt/en/blog/?category=AI%20%26%20Automation)
- [Security & Governance 1](https://www.avantit.pt/en/blog/?category=Security%20%26%20Governance)
- [Microsoft 365, Productivity 1](https://www.avantit.pt/en/blog/?category=Microsoft%20365%2C%20Productivity)
- [Data & Analytics 1](https://www.avantit.pt/en/blog/?category=Data%20%26%20Analytics)
- [Power BI 1](https://www.avantit.pt/en/blog/?category=Power%20BI)
- [Teams 1](https://www.avantit.pt/en/blog/?category=Teams)
- [DevOps 1](https://www.avantit.pt/en/blog/?category=DevOps)
- [AI 1](https://www.avantit.pt/en/blog/?category=AI) 

### Hot Topics

 
#CoPilot 
#Power Platform 
#Security 
#SharePoint 
#AI 
#Teams 

### Editorial Calendar

 
- FEV 02 Disponível Segurança em Power Apps: Guia para CTOs 
- FEV 05 Disponível Custo oculto da entrada manual de dados 
- FEV 09 Planeado Quanto custam processos manuais à sua empresa 